The project

The project involves the complete replacement of the water networks of some roads, with the installation of about 1950 m of new PEAD pipes that will replace the existing fibre cement pipes. The intervention is part of the scheduled maintenance activities that CAP Group periodically carries out on the water networks, replacing the particularly dated sections of the network as a precautionary measure.

In detail

The water network serving the residential sector in the area between Via Giacomo Frassi, Via Giardino and Via dei Gelsi has water leakage problems. This criticality was found by comparing different data: the water balance sheets, the reports received by CAP Group and the samples analysed by the Aqueduct Systems Efficiency Office.

Since the existing network is made of fibre cement, once the new pead network was built, it was decided to remove and dispose of the old one in accordance with current regulations, thus guaranteeing the future safety of operators and people residing in the area. While underground and intact, fibre cement pipes are not dangerous to public health, but they require special maintenance which is carried out in absolute safety. For this reason, the removal of the pipelines was entrusted to a specialised company registered in the National Register of Environmental Managers under category 10, “Reclamation of goods containing asbestos”.

The average excavation depth is -1.40 metres from the surface. At the end of the works, a temporary restoration of the road surface is carried out. The final restoration and horizontal signage are completed after the necessary settling time of the ground.

Street Length m Diameter mm Where
Papa Giovanni XXIII 335 180 From Via Giardino no. 1 to no. 30
Dei Giacinti 65 110 From Via dei Pini no. 1 to no. 8
Dei Pini 210 160 From Via Giardino to the intersection with Via 8 Giugno 1859
Degli Abeti 130 160 Between Via dei Pini and Via Papa Giovanni XXIII
Dei Gladioli 120 110/160 From Via degli Olmi no. 1 to no. 14
8 Giugno 1859 70 160 From Via dei Pini to the intersection with Via dei Tigli
Degli Ulivi 70 180 From Via dei Pini to the intersection with Via dei Platani
Degli Olmi 240 180 Between Via dei Pini and Via dei Gladioli
Dei Platani 185 180 Between Via dei Gladioli and Via Papa Giovanni XXIII
Dei Gigli 110 160 Between Via Giardino and Via Giovanni Falcone
Dei Gelsi 250 180 rom Via degli Olmi to the intersection with Via dei Cedri
text-slider-background text-slider-background text-slider-background
  • Work plan
  • Phase 1
  • Phase 2

The work plan is submitted to the ATS and the Municipality 30 days before the start of works in order to obtain approval. The activities are carried out by highly specialised companies and technicians, registered in the National Register of Environmental Managers and authorised for the reclamation of asbestos and the transport of hazardous waste. Works management and safety coordination are entrusted to CAP Group technicians.
Our first objective is the safety of those who work at the worksite and transit or reside nearby. The first measures for establishing safety were: identification and mapping of the underground networks (tracking, depth, materials) followed by specific surveys on the territory (geological, geophysical and sampling).

Before working on the concrete - asbestos network, the new steel network is built. The first part of the work plan consists of the installation and commissioning of the new network, which is first tested and activated. Then the fibre cement network section is decommissioned, while the water that reaches the citizens already passes through the newly laid network. This working technique makes it possible to avoid interrupting the water supply during the works for replacing the water network.

Subsequently, the old fibre cement network is removed. This phase of the works involves various safety measures to guarantee the safety of those working at the worksite and any citizens who transit or reside nearby.

Contacts

If you would like to make a report or learn more about the issues related to this worksite, write us!